Tropical Depression #AgatonPH Update As of 11 April 2022 / 5:00PM

The following transmission line has been restored:
Ormoc-Baybay 69kV Line
Date/Time Out: 10 April 2022 / 10:33PM
Date/Time Restored: 11 April 2022 / 2:51PM
Customer affected: LEYECO IV, LEYECO V
The following transmission lines are unavailable:
Ormoc-Maasin 138kV Lines 1 and 2
Date/Time Out: 11 April 2022 / 12:03AM
Customer affected: LEYECO V, BLCI, BOHECO I, BOHECO II
Maasin-Baybay 69kV Line
Date/Time Out: 11 April 2022 / 12:03AM
(affected by outage of Ormoc-Maasin 138kV Lines 1 and 2)
Maasin-Ubay 138kV Line
Date/Time Out: 11 April 2022 / 12:03AM
(affected by outage of Ormoc-Maasin 138kV Lines 1 and 2)
NGCP has mobilized its line crews and is currently conducting patrols to inspect and assess the impact of the tropical depression to its operations and facilities, and simultaneous restoration activities are being conducted on the areas already accessible.
Please note that loss of power may be caused by affected transmission facilities of NGCP or distribution facilities of local distribution utilities or electric cooperatives. Specific cities and municipalities affected by the power interruptions are determined by concerned Distribution Utilities, unless the outage affects the entire franchise area. ###

Don't hesitate to contact us. We will answer you soon!

Visitor Counter

0 0 3 9 4 0

Contact Information

Address

Government Center, Alibagu, City of Ilagan, Isabela

Phone Numbers

Globe: 0956-994-6944

Smart: 0929-663-4511

Follow us
Copyright © 2018. Isabela II Electric Cooperative. All rights reserved.

POWERED BY:

Official Website of Isabela II Electric Cooperative
error: Content is protected !!