Power Monitoring Update (Typhoon Crising)
#NEAUpdate | The Benguet Electric Cooperative (BENECO) and Abra Electric Cooperative (ABRECO) continue repairing their damaged facilities in the aftermath of severe tropical storm ‘Crising’ with a total of 1,587 households due for power restoration.
As of 9:00 a.m. on 22 July 2025, the NEA Disaster Risk Reduction and Management Department (DRRMD) reported that 40 out of the 41 (97.56%) affected municipalities under the service areas of affected electric cooperatives (EC) have been energized.
Initial estimated cost of damage to EC infrastructure reached almost P1.63-million in the franchise areas of BENECO, MOPRECO in the Mountain Province and ZAMECO 2 in Zambales.
#PowerUpdate
#CrisingPH