NGCP NOTICE OF POWER SERVICE INTERRUPTION October 19, 2019 | Saturday

•October 19, 2019, | Saturday

•7:00am – 5:00pm

•Municipality of Aurora, Benito Soliven, Burgos, Gamu, Mallig, Naguilian, Quezon, Quirino, Roxas, San Manuel, San Mariano, City of Ilagan (except San Isidro to Divisoria), Isabela.

•To implement 69KV Bus Works under the ongoing North Luzon Substation Upgrading Project at Gamu Substation.
To implement assembly of New 100MVA XIAN Transformer #2 of Gamu Substation.

We shall be putting them back into services as soon as the aforementioned activity is completed without prior notice.

For your information and guidance.