Luzon grid status, 1 December 2022
Luzon grid status, 1 December 2022:
Yellow Alert
1:00PM-8:00PM
Available Capacity – 11,166MW
Peak Demand – 10,455MW
Five (5) power plants are on forced outage, while three (3) others are running on derated capacities, for a total of 2,115MW unavailable to the grid.