EWC to Finish Construction of Pagbilao LNG Power Plant Project

#EnergyNews | The EWC gas-fired power plant was 80-percent done by 2021 but the company decided to hold off further construction to await the completion of the NGCP project completion of its switchyard, to which the EWC would interconnect to get to online with the Luzon grid. The NGCP expected four power plants around it to interconnect to the Luzon Grid. | via SunStar 📰