2022 National and Local Elections Power Situation Update As of 9 May 2022 / 1:00PM
NGCP’s transmission lines and facilities are under normal operations.
Power supply and demand in all three grids are as follows:
Luzon
Capacity – 14,043MW
Demand – 8,035MW
Visayas
Capacity – 2,836MW
Demand – 1,541MW
Mindanao
Capacity – 3,115MW
Demand – 1,238MW